by
Michelle Wathen
|
Mar 7, 2019
|
Community
As part of the first phase of East Leeds Orbital Route, we have been improving a number of existing Outer Ring Road junctions. As part of our commitment to replace trees lost through this work and to enhance the area at the Roundhay Park Lane junction we will be...
by
Michelle Wathen
|
Mar 7, 2019
|
Community
The ELOR project team recently welcomed two students from Leeds City Academy. Both students worked with the engineering team and the quantity surveying team. The students had the chance to gain real hands on experience of working on the scheme, as well as...
by
Michelle Wathen
|
Mar 7, 2019
|
Community
On Saturday 23rd March at 4pm members of the ELOR Project Team (The Fabsailors) will be abseiling down the CLV building in Leeds City Centre. The CLV building is one of the tallest buildings in the north of England, standing at 300 foot high. Our team of 8 are...
by
Michelle Wathen
|
Mar 7, 2019
|
Project Timeline
A6120 East and West bound the construction of the new footpath/cycleway has continued with the surface water drainage now complete. Working with Leeds Parks and Countryside the underground tree architecture has been installed ready for tree planting later in the year....
by
Michelle Wathen
|
Mar 7, 2019
|
Project Timeline
On the A6120 works has continued on the central island along with commencement of the new carriage way widenings on the north and south side of the central reservation to the east. These areas will be surfaced in the next few weeks. Works are now progressing on the 4...